As of Jul 6, 2026
HERON EXECUTION DASHBOARD
Cross-project roadmap by standardized workstream
Weekly roadmap view starting from today. Fixed phase dates are used as baseline; only the visible window moves with the current date.
Standardized workstream & symbols
feature requirementmigration requirementproject resource on boardfeasibility study and timeline planDesignDeliver-developmentDeliver-SITDeliver-E2E testingUAT initializationKU Training and TestingCut-overHypercare◇Milestone⚑Go-live--TBC / tentative
July
August
September
October
November
Week of
Jul 10Jul 13Jul 20Jul 27Aug 3Aug 10Aug 17Aug 24Aug 31Sep 7Sep 14Sep 21Sep 28Oct 5Oct 12Oct 19Oct 26Nov 2Nov 9Nov 16Nov 23Nov 30
IB/FR PPK pilot
RO pilot
DACH PPK pilot
UK migration
X2
⚑GL
VN migration
X2
⚑GL
IB deployment
⚑GL
ROBA deployment
No active stage block in the selected horizon
DACH deployment
No active stage block in the selected horizon
MFS PPV pilot
MFS PPK pilot
HERON Project Milestone Status
X0
X1
X2
GL
S
X3
CLOSED
CXS EU Effitires

IB deployment



ROBA deployment


DACH deployment
DACH pilot
RO pilot

IB/FR pilot
PL pilot
CXS NA MFS
MFS-PPV pilot
MFS-PPV deployment
MFS-PPK pilot
MFS-PPK deployment
CXS UK
UK migration
DCEC ENGAGE


DE/FR/US pilot
REGION
VN migration

AMS
Project Execution Details and Short-term Actions
Completed = milestone / task reached 100% complete.On track = scheduled, on schedule, ahead of schedule, or in progress with no current delivery risk.Pending = TBC / pending / not yet confirmed.Blue action text = concrete short-term action or follow-up note under the task.
X0
Apr 27, 2026
X1
May 28, 2026
X2
Jul 28, 2026
GL
Sep 14, 2026
X3
TBC
Last week completed
TTMP UK: New tenant build - v3.9.3
Jun 30, 2026
This week ongoing
Gathering the UK set-up configuration files
Scheduled
Jul 17, 2026
Short-term actions for future tasks
Gathering the UK set-up configuration filesOn scheduleJul 17, 2026
to confirm the defect rules configuration file and approach.
Data migration dev for UK (TTMP->FlowLink)To be confirmedTBC
to confirm the Open defect UAT init. date by Mei and Loic
X0/X1
Jul 6, 2026
X2
TBC
GL
Nov 16, 2026
X3
TBC
This week ongoing
Complete the BA test cases in TAMS
Jul 10, 2026
Global SIT with I2A
To be confirmed
Jul 23, 2026
Oplink for MVP1 - (extend to 10.5)
Scheduled
Sep 7, 2026
HCRC for MVP1
Ahead of schedule
Sep 7, 2026
HCCV for MVP1
Ahead of schedule
Sep 7, 2026
HCIL for MVP1
Ahead of schedule
Sep 7, 2026
HCMT for MVP1
Scheduled
Sep 7, 2026
Global SIT with EMC2
To be confirmed
Sep 25, 2026
Short-term actions for future tasks
HCMT for MVP1ScheduledSep 7, 2026
to confirm the migration scope and requirements by July 10
E2E testing by SE - 3.10.20nanSep 25, 2026
confirm the SE testing plan by July 10.
X0
May 12, 2026
X1
Jun 2, 2026
X2
Oct 23, 2026
GL
Nov 9, 2026
X3
TBD
Last week completed
VN: Vietnamese checking in single language excel file by KU
Jul 3, 2026
This week ongoing
HCDM dev for VN PBI report data feeding
To be confirmed
Sep 22, 2026
to align the solution and confirm the target finish date by Loic.
HCMT dev for VN historical insp. data migration
To be confirmed
Sep 22, 2026
to align the solution and confirm the target finish date by Loic.
Short-term actions for future tasks
HCDM dev for VN PBI report data feedingTo be confirmedOct 5, 2026
to align the solution and confirm the target finish date by Loic by August
HCMT dev for VN historical insp. data migrationTo be confirmedOct 5, 2026
to align the solution and confirm the target finish date by Loic by August.
X0Jun 5, 2026
X1TBC
X2TBC
GLJan 2027
X3TBC
X0Jul 1, 2026
X1TBC
X2TBC
GLJan 2027
X3TBC
X0
Oct 24, 2025
X1
Apr 28, 2026
X2
Jan 15, 2027
PPV P GL
Jan 25, 2027
PPV D GL
Feb 22, 2027
PPK P GL
Aug 16, 2027
PPK D GL
Feb 22, 2027
X3
TBC
Last week completed · MFS-PPV
Feasibility of deliver the 1st PPV pilot with manual creation
Jun 30, 2026
Last week completed · MFS
Sandbox trial feedback in Tenant-1 pre. - for PI11 planning
Jul 3, 2026
This week ongoing · MFS-PPV
PPV: BA Test cases
To be confirmed
Jul 31, 2026
Short-term actions for future tasks
PPK: Exchange new TAMSBehind scheduleJul 10, 2026
to refine the PPK TAMS tickets by Sylvie based on the aligned points with Steve and Yuming.
PPV: BA Test casesTo be confirmedAug 20, 2026
to confirm the TAMS ticket scope with Sylvie by July 10. / waiting for some feedback from OpLink team for the alignment of requirements. / share the testing process and R&R with the MFS team.
OpLink translation - en_USnanOct 30, 2026
continuously check the en_US for the latest generated translations by the new project leader.
OpLinkTo be confirmedNov 6, 2026
to confirm timeline plan for the PPV pilot (maybe in PI11 in Mid-Sept.)
HCPFTo be confirmedNov 6, 2026
to confirm timeline plan for the PPV pilot (maybe in PI11 in Mid-Sept.)
Go live - PPK pilotTo be confirmedAug 16, 2027
to see if the IBIS can finish the dev in Q1


DCEC ENGAGE · DE/FR/US pilot
X0
X1
Jul 17, 2026
X2
TBC
GL
Mar 2027
X3
TBC